Step 1 - Describe databases
========================================
The first step is to describe databases used in the replication. There are usually 
two of them (source and target); however, there can be just one (when
source and target is the same) or more than two (one-to-many or other complex 
configurations.)  
Following databases are now configured:
1: Oracle orcl, SYS/**, SYSTEM/*, dbvrep/**, USERS/TEMP, dbvrep/, ASM:YES,TZ: +00:00 
2: Oracle test11202, SYS/**, SYSTEM/*, dbvrep/**, USERS/TEMP, dbvrep/, ASM:NO,TZ: +00:00 
3: Oracle dbvisit210_d112f, SYS/**, SYSTEM/*, dbvrep/**, USERS/TEMP, dbvrep/,  ASM:NO,TZ: +00:00 
Enter number of database to modify it, or "add", or "done": [done]

...

No Format
bgColorCCC
Step 2 - Replication pairs
========================================
The second step is to set source and targets for each replication pair. This is 
usually just choosing the first database as source and the second one as
target, but many more configurations are possible. 
Following replication pairs are now configured:
Following replication pairs are now configured:
1: orcl (Oracle) ==> test11202 (Oracle), DDL: yes, fetcher: no, process suffix: (no  suffix), compression: no, encryption: no, network timeout: LAN 60, prepare type: single-scn, data load: dp_networklink

2: orcl (Oracle) ==> dbvisit210_d112f (Oracle), DDL: yes, fetcher: no, process suffix: (no suffix), compression: 1no, encryption: no, network: LAN timeout: 60, prepare type: single-scn, data load: dp_networklink
Enter number of replication pair to modify it, or "add", or "done": [done]

...

No Format
bgColorCCC
Step 4 - Process configuration
===Following processes are defined:
1: MINE on orcl
Host: rac11202node1, SMTP: YES, SNMP: NO
2: APPLY on test11202
Host: dbvisit400, SMTP: YES, SNMP: NO
3: MINE1 on orcl
Not used, work done by MINE.
4: APPLY1 on dbvisit210_d112f
Host: dbvisit210, SMTP: YES, SNMP: NO
Enter number of process to modify it, or "done": [done]

...

Note

Note that the MINE process MINE is shared for both the APPLY processes APPLY and APPLY1. The process MINE1 is not used because it is more efficient to only use 1 MINE process (MINE) for all the target databases.
The Next steps (Nextsteps.txt) displayed when the setup wizard has completed will show the actions to be taken for each server and will include the steps that need to run for all target databases.